Code Reference (NEC)

  • NEC 110 – General installation

  • NEC 706 – ESS

  • NEC 705 – Interconnection

  • NEC 250 – Grounding

  • NEC 408 – Panelboards

What Inspectors Verify

  • UL listings (panel, breakers, ESS)

  • Conductor sizing

  • Grounding and bonding

  • Clear labeling

  • Working clearances


Documentation to Provide

  • Single-line diagram

  • Product listings and certifications

  • Utility interconnection approval

  • Commissioning confirmation


Final Inspection Checklist

  • Internet connected

  • CTs verified

  • Backup mode tested

  • Panel labeled

  • App commissioning complete