Installation with Generators

Kora supports generator integration using a dedicated generator input and breaker. Kora manages transfer logic and load coordination.

Written by Paige Tranchina
Updated over 2 months ago

Code Reference (NEC)

  • NEC 702 – Optional Standby Systems

  • NEC 445 – Generators

  • NEC 250 – Grounding and bonding

  • NEC 110.20 – Transfer equipment ratings

Generator Requirements

  1. Single-phase residential generators

  2. Compatible start/stop control (if auto-start)

  3. Proper grounding and neutral configuration

  4. ≤ 20 kW


Installation Steps

  1. Install generator breaker in designated slot

  2. Land L1, L2, Neutral, Ground on designated terminals

  3. Install generator CTs if required

  4. Connect auto-start wiring if applicable

  5. Keep auto-start wiring isolated from HV conductors


Testing

  • Simulate outage

  • Confirm generator start and load acceptance

  • Verify priority circuits behave correctly